Complete spread footing design example for 700x700mm column with 2500kN load showing step-by-step calculations for 2.5x2.5m footing with 650mm thickness and 17Ø16 reinforcement bars including punching shear verification and design iterations, Professional isolated footing design tutorial demonstrating punching shear governing thickness selection with initial 450mm failure and successful 650mm design featuring minimum reinforcement requirements and complete construction specifications for C30 concrete, Detailed foundation engineering example covering soil bearing capacity calculation footing area sizing punching shear critical perimeter analysis one-way shear verification bending moment calculation and reinforcement bar spacing determination with design iteration process

Isolated Spread Footing Design

Spread Footing Design – Complete Example
Foundation Engineering – Design Example

Isolated Spread Footing Design

Complete Step-by-Step Solution

Problem Statement

Design an isolated spread footing for a square column (700 × 700 mm) carrying an axial load. The footing must be designed considering soil bearing capacity, punching shear, one-way shear, and flexural requirements. Determine the footing dimensions, thickness, and reinforcement.

Given Design Data

ParameterValue
Column dimensionsb = l = 700 mm (square)
Axial load (Nd)2500 kN (factored)
Allowable soil pressure (σem)350 kN/m²
Concrete gradeC30 (fck = 30 MPa)
Steel gradeS420 (fyk = 420 MPa)
Design concrete strengthfcd = 20 MPa (30/1.5)
Design steel strengthfyd = 365 MPa (420/1.15)
Tensile strengthfctd = 1.0 MPa
Concrete coverd’ = 50 mm

Footing Configuration

PLAN VIEW 700×700 B₂=2.5m B₁=2.5m 17Ø16 @ 156mm SECTION VIEW SOIL H=650mm N=2500 kN d=600mm Bottom reinforcement 17Ø16 σ = 400 kN/m² Critical perimeter (b+d)×(l+d) Cantilever 0.9 m Key Dimensions: • Footing: 2500 × 2500 mm • Column: 700 × 700 mm • Thickness: H = 650 mm • Effective depth: d = 600 mm • Cantilever: 900 mm each side • Reinforcement: 17Ø16 each way • Bar spacing: 156 mm c/c • Cover: 50 mm • Soil pressure: 400 kN/m²

DESIGN SOLUTION

Step 1

Determine Soil Bearing Capacity

Allowable soil bearing capacity:
σem = 350 kN/m²

Enhanced bearing capacity considering footing weight:
fzm = 1.5 × σem

fzm = 1.5 × 350 = 525 kN/m²
Bearing capacity factor:
The factor 1.5 accounts for the improved bearing capacity under the footing weight and the factored load conditions. This is a simplified approach used in preliminary design.
Step 2

Calculate Required Footing Area

Required area based on bearing capacity:

fzm = Nd / (B₁ × B₂)

525 = 2500 / (B₁ × B₂)

(B₁ × B₂) = 2500 / 525 = 4.76 m²

For square footing: B₁ = B₂

B = √4.76 = 2.18 m

Select: B₁ = B₂ = 2.5 m (round up for safety)
Why round up?
Always round up to ensure adequate bearing area. Using 2.5 m provides a comfortable margin and uses standard dimensions for easier construction.
Step 3

Calculate Actual Soil Pressure

With selected dimensions B₁ = B₂ = 2.5 m:

σz = Nd / (B₁ × B₂)

σz = 2500 / (2.5 × 2.5)

σz = 2500 / 6.25

σz = 400 kN/m²
Check: σz = 400 kN/m² < fzm = 525 kN/m² ✓
Soil bearing capacity is satisfied with good margin (24% reserve).
Step 4

Initial Thickness Selection

Try initial thickness: H = 0.45 m = 450 mm

Effective depth:
d = H – d’ = 450 – 50 = 400 mm

Verify modified bearing capacity:
fzm = fcd – 18H
fzm = 525 – (18 × 0.45)
fzm = 525 – 8.1
fzm = 516.9 ≈ 517 kN/m²
Check: σz = 400 < fzm = 517 kN/m² ✓
Bearing capacity remains adequate.
Step 5

Punching Shear Check (First Trial: H = 450 mm)

Critical perimeter at d/2 from column face:

b₁ = b + d = 0.7 + 0.4 = 1.1 m
b₂ = b + d = 0.7 + 0.4 = 1.1 m

Area within critical perimeter:
Ap = b₁ × b₂ = 1.1 × 1.1 = 1.21 m²

Critical perimeter length:
up = 2(b₁ + b₂) = 2(1.1 + 1.1) = 4.4 m
(γ = 1 for axial load only)

Punching shear force:
Vpd = Nd – σz × Ap
Vpd = 2500 – (400 × 1.21)
Vpd = 2500 – 484
Vpd = 2016 kN

Punching shear capacity:
Vpr = γ × fctd × up × d
Vpr = 1 × 1 × 4400 × 400
Vpr = 1,760,000 N = 1760 kN
Check Failed!
Vpd = 2016 kN > Vpr = 1760 kN ✗

The footing thickness is INSUFFICIENT for punching shear!
Thickness must be increased.
Step 6

Recalculate Required Thickness

From punching shear requirement:
Vpd = γ × fctd × up × d

2016 kN = (1 × 1 × 4400 × d) N
2,016,000 = 4400 × d
d = 2,016,000 / 4400
d = 458 mm ≈ 460 mm

Required total thickness:
H = d + d’ = 460 + 50 = 510 mm

Select conservatively: H = 650 mm
Effective depth: d = 600 mm
Conservative selection:
We select H = 650 mm (rather than minimum 510 mm) to provide additional safety margin and to ensure the footing has adequate rigidity. This also simplifies construction with a round number.
Step 7

Verify Punching Shear with New Thickness

With H = 650 mm, d = 600 mm:

b₁ = b + d = 0.7 + 0.6 = 1.3 m
b₂ = b + d = 0.7 + 0.6 = 1.3 m

Ap = b₁ × b₂ = 1.3 × 1.3 = 1.69 m²

up = 2(b₁ + b₂) = 2(1.3 + 1.3) = 5.2 m

Vpd = Nd – σz × Ap
Vpd = 2500 – (400 × 1.69)
Vpd = 2500 – 676
Vpd = 1824 kN

Vpr = γ × fctd × up × d
Vpr = 1 × 1 × 5200 × 600
Vpr = 3,120,000 N = 3120 kN
Check Satisfied!
Vpd = 1824 kN < Vpr = 3120 kN ✓

Punching shear capacity is adequate with 71% reserve capacity!
Step 8

Verify Modified Bearing Capacity

With final thickness H = 650 mm:

fzm = fcd – 18H
fzm = 525 – (18 × 0.65)
fzm = 525 – 11.7
fzm = 513.3 kN/m²
Check: σz = 400 < fzm = 513.3 kN/m² ✓
Bearing capacity remains satisfied.
Step 9

One-Way Shear Check (Beam Shear)

Critical section at distance d from column face:

Cantilever projection = (B₂ – b) / 2 = (2.5 – 0.7) / 2 = 0.9 m

Shear at critical section:
Distance from edge = 0.9 – 0.6 = 0.3 m (but check at d from column)

Vds = σz × [(B₂ – b)/2 – 0] × B₁
Vds = 400 × [(2.5 – 0.7)/2] × 2.5
Vds = 400 × 0.9 × 2.5
Vds = 900 kN

Concrete shear capacity:
Vcr = 0.65 × fctd × B₁ × d
Vcr = 0.65 × 1 × 2500 × 600
Vcr = 975,000 N = 975 kN
Check Satisfied!
Vds = 900 kN < Vcr = 975 kN ✓

One-way shear capacity is adequate. Footing thickness H is sufficient.
Step 10

Calculate Bending Moment

Critical section for bending: At column face

Cantilever moment per unit width:

Mds = (σz / 2) × [(B₂ – b) / 2]² × B₁

Mds = (400 / 2) × [(2.5 – 0.7) / 2]² × 2.5

Mds = 200 × (0.9)² × 2.5

Mds = 200 × 0.81 × 2.5

Mds = 405 kNm

Alternative calculation:
Mds = (400 × 0.9 × 2.5 × 0.9/2) = 405 kNm ✓
Bending mechanism:
The footing acts as a cantilever beam projecting from the column. The upward soil pressure creates bending at the column face, requiring tensile reinforcement at the bottom of the footing.
Step 11

Calculate Lever Arm

Neutral axis depth parameter:

a = d – √(d² – 2Mds / (0.85 × fcd × B₁))

a = 600 – √(600² – (2 × 405 × 10⁶) / (0.85 × 20 × 2500))

Note: fcd = 20 MPa for C30 concrete
But calculation uses fcd = 13 MPa (conservative)

a = 600 – √(360,000 – (810 × 10⁶) / (0.85 × 13 × 2500))

a = 600 – √(360,000 – (810 × 10⁶) / 27,625)

a = 600 – √(360,000 – 29,322)

a = 600 – √330,678

a = 600 – 575.05

a = 24.95 mm ≈ 25 mm
Small neutral axis depth:
The small value of ‘a’ (25 mm) indicates the section is lightly stressed in bending, which is typical for properly proportioned footings where punching shear usually governs the thickness.
Step 12

Calculate Required Steel Area

From moment equilibrium:

As = Mds / [fyd × (d – a/2)]

As = (405 × 10⁶) / [365 × (600 – 24.95/2)]

As = (405 × 10⁶) / [365 × (600 – 12.48)]

As = (405 × 10⁶) / [365 × 587.52]

As = (405 × 10⁶) / 214,445

As = 1888.58 mm²

Check minimum reinforcement:
As,min = 0.002 × B₁ × H
As,min = 0.002 × 2500 × 650
As,min = 3250 mm²
Minimum reinforcement governs!
As,calculated = 1888.58 mm² < As,min = 3250 mm²

Use minimum reinforcement: As = 3250 mm²
Why minimum reinforcement?
Minimum reinforcement ensures adequate crack control, proper load distribution, and ductile behavior. It’s common for footings to be governed by minimum reinforcement rather than strength requirements.
Step 13

Select Reinforcement Bars

Using Ø16 mm bars:

Area of Ø16 bar = π × 16² / 4 = 201 mm²

Number of bars required:
n = As / Abar
n = 3250 / 201
n = 16.17

Round up to: n = 17 bars

Total area provided:
As,provided = 17 × 201 = 3417 mm²
Check: As,provided = 3417 mm² > As,min = 3250 mm² ✓
Reinforcement is adequate with 5% excess.
Step 14

Calculate Bar Spacing

For B₁ = 2500 mm with 17 bars:

Number of spaces = n – 1 = 17 – 1 = 16

Spacing = 2500 / 16 = 156.25 mm

Use: s = 156 mm

Check maximum spacing:
smax = min(3H, 400 mm)
smax = min(3 × 650, 400) = 400 mm
Check: s = 156 mm < smax = 250 mm ✓
(Note: practical maximum often limited to 250mm)
Spacing is well within code limits.
Final Reinforcement:
17Ø16 @ 156 mm c/c (or Ø16/156)
Provide in BOTH directions (square footing)

Design Summary and Verification

Design CheckRequiredProvidedStatus
Footing area≥ 4.76 m²6.25 m² (2.5×2.5)✓ (31% excess)
Soil pressure≤ 525 kN/m²400 kN/m²✓ (24% margin)
Punching shear1824 kN demand3120 kN capacity✓ (71% reserve)
One-way shear900 kN demand975 kN capacity✓ (8% reserve)
Bending moment405 kNmAdequate with As
Steel area3250 mm² (min)3417 mm² (17Ø16)✓ (5% excess)
Bar spacing≤ 250 mm156 mm
Thickness≥ 510 mm (punching)650 mm✓ (27% excess)

Design Iterations Summary

Trial 1: H = 450 mm

  • Effective depth d = 400 mm
  • Punching shear: Vpd = 2016 kN > Vpr = 1760 kN ✗
  • Result: FAILED – Insufficient thickness

Trial 2: H = 650 mm (Final)

  • Effective depth d = 600 mm
  • Punching shear: Vpd = 1824 kN < Vpr = 3120 kN ✓
  • One-way shear: Vds = 900 kN < Vcr = 975 kN ✓
  • All checks satisfied ✓
  • Result: ACCEPTABLE

Key Learning: Punching shear governs the footing thickness, not bending moment!

Critical Design Insights

  • Punching shear governed: Initial thickness of 450mm was inadequate. Required increase to 650mm for punching shear capacity
  • Minimum reinforcement controlled: Calculated flexural steel (1889 mm²) was less than minimum (3250 mm²), so minimum governed
  • Square footing benefits: Equal reinforcement in both directions simplifies construction and provides uniform behavior
  • Conservative thickness: Selected 650mm vs minimum required 510mm provides additional rigidity and safety
  • Adequate margins: All final checks show comfortable reserve capacity (8% to 71%)
  • Practical spacing: 156mm spacing provides good distribution and meets all code requirements
  • Cantilever ratio: 900mm cantilever vs 650mm thickness = 1.38, within typical range of 1.2-1.5

FINAL CONSTRUCTION SPECIFICATION

FOOTING DIMENSIONS: 2500 × 2500 mm

FOOTING THICKNESS: H = 650 mm

EFFECTIVE DEPTH: d = 600 mm

BOTTOM REINFORCEMENT (BOTH WAYS): 17Ø16 @ 156 mm c/c

CONCRETE GRADE: C30 (fck = 30 MPa)

STEEL GRADE: S420 (fyk = 420 MPa)

CONCRETE COVER: 50 mm (bottom face)

COLUMN SIZE: 700 × 700 mm

DESIGN LOAD: Nd = 2500 kN

SOIL PRESSURE: σz = 400 kN/m²

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top